Concrete strike’s impact on West Seattle Bridge timeline unclear as SDOT makes final pours

The Seattle Department of Transportation (SDOT) still hopes to open the West Seattle Bridge in “mid-2022,” according to a spokesperson with the transportation agency. A to-be-announced, updated timeline will be delivered on June 9.

“Our construction contractor is planning to finish the final structural concrete pours this week, marking the end of a challenging process that has affected our reopening schedule,” SDOT’s Ethan Bergerson wrote to MyNorthwest.

SDOT contracts with Kraemer North America for the West Seattle Bridge. A Kraemer spokesperson declined to comment on whether the reopening would be pushed beyond that mid-2022 timeframe.

“Some delays have been associated with the concrete strike earlier in the year. Those